PE Pipelines
Large Diameter Pipelines
Survey & Design
Pump Stations
Storages
Commissioning – Operations Training
Projects
Construction Plant & Equipment
Innovation
Careers
News Items
   
 
Year Client Project Location Contractual Position Contract Duration Details. Pipe dia, length, scope
2005 Santos Onshore Facility Works & Mainline Valve Installation Pt Campbell Vic Head Contractor 6 Weeks DN300 ML Valve, Civil & Pipe work Installation
2005 GasNet Australia Pakenham Bypass Project Pakenham, Vic Head Contractor 6 Weeks Approx 750m of 150mm supply pipeline
2005 Santos Casino Onshore Gas Pipeline Pt Campbell Vic Head Contractor 12 weeks 12km of DN300 Steel welded Pipe 36km of DN50 Steel welded Pipe
2004 John Holland Constructions Regional Fast Rail Sydenham - Bendigo Sub Contractor 24 weeks 80km Trenching
2004 SA Water Clare Valley Stage 3 - Reticulation Clare Valley South Aust. Head Contractor 11 weeks Approx 8km township reticulation
2004 Clarence City Council Tasmania Coal River Valley Water Recycling Scheme Stg 2 Hobart, Tasmania Head Contractor 16 weeks 18.5 km Pressure Pipeline
2004 Dept. of Infrastructure, Energy & Resources Tas Coal River Valley Water Recycling Scheme Stg 1 Hobart, Tasmania Sub Contractor 8 weeks Installing 6.3km Pipeline
2003 South Australia Water Clare Valley Water Supply Stage 2 Clare Valley South Aust. Head Contractor 20 weeks Approx 37km Water Supply Pipeline
2003 Goulburn Valley Water Welsford St Water Treatment Plant Pipeline Shepparton VIC Head Contractor 16 weeks Approx 10km Alum sludge outfall pipeline
2003 South Australia Water Clare Valley Water Supply Stage 1 Clare Valley, South Aust. Head Contractor 12 weeks 13.8 km Water Supply Pipeline
2003 Goulburn Murray Water Normanville Pipeline Normanville VIC Head Contractor 22 weeks 190km Pressure Pipeline of assorted diam.
2003 Clough Engineering HDD Drill Bass Gas Shore Crossing Kilcunda VIC Subcontractor 12 weeks 355od Steel Gas Pipeline for Horizontal Drill Section
2003 Quiprite Yungera trenching Robinvale, VIC Sub contractor   47km trenching for AG. Drain
2003 Quiprite Boort Irrigation Boort, VIC Sub contractor 4 weeks Water Main
2002 Goulburn Murray Water Woorinen Pipeline Project Woorinen, VIC Head Contractor 32 weeks 80km of water line ranging from 225 to 1000 diam
2002 South Australian Water Poochera to Streaky Bay Pipeline Streaky Bay, SA Head Contractor 24 weeks Design & Construct 55km of water line from 150 to 200 diam
2001 Walter Construction Gerringong to Gerroa Sewerage Scheme Gerringong NSW Subcontractor 20 weeks 9km of Sewerage Reticulation ranging from 100 to 450 diam
2001 Lend Lease Developments Rising Main No.1 Mango Hill Head Contractor 12 weeks 2km of 375mm DICL, under road bore & assoc. Works
2001 Lend Lease Developments Kerr Rd. Trunk Water Main Dakabin / Mango Hill Head Contractor 12 weeks 1.2km of 960 diam MSCL pipe, under road bore, etc.
2001 Barossa Infrastructure Limited Barossa Water Supply Project Barossa Valley, SA Head Contractor 32 weeks Design & Construct 187km of water line ranging from 150 to 960 diam
2001 Nth Qld Water Douglas to Mt Jack Water Pipeline Nth Townsville Head Contractor 24 weeks 7.5km of fully welded 1290 diam MSCL water pressure main
2000 Transfield Construction Mittagong Sewerage Reticulation Mittagong NSW Subcontractor 45 weeks 27km of 150 to 600 diam gravity and rising mains
2000 Vivendi Water Aqua 2000, Transmission Pipeline Bendigo VIC Subcontractor 40 weeks 25km of 300 to 1167 DICL & MSCL pipelines
2000 Goulburn Valley Water Wandong Reticulation Sewerage Scheme Wandong VIC Head Contractor 36 weeks 27 km of 200 mm dia PVC gravity pipeline and rising mains
1999 NSW Dept of Public Works Wongabon Water Reticulation Dubbo NSW Head Contractor 16 weeks 24 km of 200 mm dia DICL water pipeline
1999 South West Water Koroit Reticulation Sewerage Scheme Koroit VIC Head Contractor 40 weeks 23 km of 150 to 300 diam gravity pipeline and rising mains
1999 Transfield Constructions Roxby Downs water transmission pipelines Stage 2 Roxby Downs Subcontractor 28 weeks 120km of DICL water pipeline
1999 Gippsland Water Neerim Sth to Noojee water supply line Neerim Sth VIC Head Contractor 20 weeks Design & Construct 16km of 200 diam water pipeline
1999 Transfield Construction Ernest Henry Water pipeline Cloncurry to Julia Creek Subcontractor 28 weeks 134 km of 660 DICL and DICL RRJ water pipeline
1998 Transfield Construction Century Zinc Queensland Subcontractor 24 weeks 300km 300mm Gas pipeline
1998 Minson Construction Chiltern Valley to Koonoomoo Gas Transmission Pipeline Cobram to Chiltern Subcontractor 28 weeks 113 km of 150mm and 200mm dia steel gas pipe
1997 Transfield Constructions Roxby Downs water transmission pipelines Roxby Downs Subcontractor 28 weeks 120km of DICL water pipeline
 
Home   |   About Us   |   QA   |   Privacy Policy   |   Contact Us

Copyright © Mitchell Water. All Rights are reserved.